Project Summary

  • Client

    Winnipeg Airport Authority 

  • Budget

    $366 Million

  • Size

    548,000 sq. ft. 

  • Delivery Model

    Design-Bid-Build

  • Year Complete 

    2010 

  • Market

    Airport

The Story

EllisDon was the General Contractor for the construction of the new 548,000 SF Air Terminal Building (ATB) for the Winnipeg Airports Authority (WAA). This contract was a major component of WAA’s total airport site redevelopment program, which had a total construction commitment of $585 million covering the period of 2007-2011.

Over and above constructing this large terminal building, the contract also included the complete renewal of the baggage handling systems, a new Central Utilities Building / Plant (CUP), as well as the construction of a 1-km underground tunnel between the ATB and CUP that connects all services.  Furthermore, the EllisDon team was required to construct a new 531-m elevated roadway and bridge that is adjacent to the new ATB, as well as complete the parkade which included car rental facilities and spaces.

Edmonton International Airport Combined Office Tower

Edmonton

The goal of this project was to provide improved airside ground operations, expanded retail ser...

More about this project

Calgary International Airport New Concourse

Calgary

EllisDon is the Construction Manager for the International Facilities Project (IFP) at the Calg...

More about this project

Calgary International Airport – International Facilities Project Terminal Expansion

Calgary

EllisDon is the Construction Manager for the International Facilities Project (IFP) at the Calg...

More about this project