Sectors
Industrial
Sub Sectors
Data Centers
Regions
Quebec
Capacity
80 MW
The Story
A leading global technology company has engaged EllisDon to provide pre-construction services for its first self-developed data center in Canada – the initial facility in a planned three-building campus that will ultimately deliver a critical load capacity of 240 MW. EllisDon is involved during the development phase to evaluate scopes of work for the initial Guaranteed Maximum Price (GMP) contracts. The project also includes close collaboration with the client and their consulting team to deliver value engineering throughout the pre-construction phase of the first building, which will provide 80 MW of critical load at full build-out.
Latest Projects
Whether you’re exploring partnership or seeking guidance on a development, we’re ready to help you move forward with confidence.
Contact Us