The Story

Upon completion of the Eighth Avenue Place East Tower, EllisDon was awarded the contract to construct the neighbouring Eighth Avenue Place West Tower.

Achievement

LEED CS Platinum

The west tower is a new 40-storey 850,000 square foot tower in downtown Calgary. A new three-storey lobby will connects the new tower to the existing east tower and winter garden. The new tower is situated diagonally across from the existing tower on the site, and will be sloped in the opposite direction from the existing tower, maximizing tower views for occupants of both towers.

Architectural crown lighting, as well as vertical light features, are incorporated into the exterior design, creating a striking effect at night. Each floor plate is approximately 22,000 square feet of Class AAA office space with floor to ceiling windows. The new tower is built on top of an existing two-storey podium and six-storey underground parkade, which was open for operation during construction.

Normal distance for a crane from the building’s core is 10 to 15 feet. The generally acknowledged record was 45 feet. We needed to go 60.

The mechanical systems feature variable air distribution system and perimeter air curtains, thermal energy monitoring and control, and state of the art building monitoring and control systems. The electrical systems feature dual telecommunications riser with access on every floor, high performance T5 lamp technology and low heat building standard lights. The unitized curtainwall is inspired by the Rocky Mountains.

The construction challenge of this project is the limited space on site, working beside the existing glass winter garden and east tower. The solution is to have just-in-time deliveries, and a specially constructed protection system for winter garden. A unique element of this project was that the building maintenance swing stage and crane was permanently mounted on top of the structure, as well as the snow and ice hot water deluge melting system.