Scope

  • Involved the construction of a two-storey greenfield utility grid control center which included 5,000 sq. ft. of white space, 750 kW of “Day 1” critical infrastructure, and provisioning for up to 3.2 MW of critical load.
  • Features three control rooms, office areas, and infrastructure space.